Ward Ii committee Unknown

Tuesday, July 19, 2022 · 5:00 PM

Location not published

No minutes have been posted for this meeting yet, so no outcomes are recorded below.

Community Voice

Unofficial, advisory polls run by this independent site, not the school board: one poll for each action item, open until the meeting is scheduled to start.

No polls are open for this meeting. A poll opens for each action item once the board posts the agenda and the wording has been reviewed.

All Community Voice polls

Documents

Documents for this meeting
DocumentVersionPostedDiscovered by JeffDavisEduLast verified
July 2022 Ward II Agenda 2ND.pdf
Agenda, 2 pages · sha256 9c1f1cd530…
v1 May 20, 2025 (server date) Nov 4, 2026 11:43 PM Nov 4, 2026 11:43 PM

Agenda items

I CALL TO ORDER

  1. I

    CALL TO ORDER

    Procedural Administrative

    Original agenda text
    I. CALL TO ORDER

II ROLL CALL FOR DETERMINATION OF A QUORUM.

  1. II

    ROLL CALL FOR DETERMINATION OF A QUORUM.

    Procedural Administrative

    COMMITTEE MEMBERS: Chairman- Phillip Arceneaux, David Capdeville, Donald
    Dees, David Doise, Denise Perry and James Segura.
    Roll Call for Ward II Committee Members for determination of a quorum:
    Arceneaux, Chairman Capdeville Dees Doise Perry Segura
    Roll Call for Other Members present:
    BORD BOUL BRUC DOB LEGER SING TRAHAN

    Original agenda text
    II. ROLL CALL FOR DETERMINATION OF A QUORUM.
    COMMITTEE MEMBERS: Chairman- Phillip Arceneaux, David Capdeville, Donald
    Dees, David Doise, Denise Perry and James Segura.
    Roll Call for Ward II Committee Members for determination of a quorum:
    Arceneaux, Chairman Capdeville Dees Doise Perry Segura
    Roll Call for Other Members present:
    BORD BOUL BRUC DOB LEGER SING TRAHAN

III VOTE TO CHANGE THE ORDER OF TOPICS TO BE ADDRESSED AND

  1. III

    TO CHANGE THE ORDER OF TOPICS TO BE ADDRESSED AND

    Action Administrative

    TO ADD NEW ITEMS NOT ON THE ORIGINAL AGENDA.

    No recorded outcome yet.

    Original agenda text
    III. VOTE TO CHANGE THE ORDER OF TOPICS TO BE ADDRESSED AND
    TO ADD NEW ITEMS NOT ON THE ORIGINAL AGENDA.
    MOTION BY: SECONDED BY: PUBLIC COMMENT DISCUSSION VOTE

IV DISCUSSION:

  1. IV.1

    Proposal to lease the old Jennings Elementary School.

    Discussion Facilities & maintenance

    Schools named: Jennings Elementary School

    Original agenda text
    1. Proposal to lease the old Jennings Elementary School.
  2. IV.2

    Guidance on what buildings will remain as part of Taxing District

    Discussion Budget & finance

    #2. Will need to provide Director of Finance Taxing District #2 guidance on
    how to allocate Maintenance Tax District 2 funds.

    Original agenda text
    2. Guidance on what buildings will remain as part of Taxing District
    #2. Will need to provide Director of Finance Taxing District #2 guidance on
    how to allocate Maintenance Tax District 2 funds.
  3. IV.3

    Current updates with the new school.

    Discussion Other

    Original agenda text
    3. Current updates with the new school.

V AGENDA ITEMS FOR CONSIDERATION

  1. V.1

    To authorize a purchase for the new Jennings Elementary School of 54 shelving

    Action Contracts & procurement $37,508.40

    units for classrooms at a total of $37,508.40 through State contract, from Virco, to
    be paid out of Ward II Construction.

    Schools named: Jennings Elementary School

    No recorded outcome yet.

    Original agenda text
    1. To authorize a purchase for the new Jennings Elementary School of 54 shelving
    units for classrooms at a total of $37,508.40 through State contract, from Virco, to
    be paid out of Ward II Construction.
    MOTION BY: SECONDED BY: PUBLIC COMMENT DISCUSSION VOTE
  2. V.2

    Grant permission to accept Change Order No. 5 on the Jennings Elementary

    Action Construction & capital $23,958,941.00

    Construction Project.
    Change Order #5 reflects the following changes:
    * 24 additional days, due to flooring manufacturing delays
    Bid Changes as follows:
    The Original Contract Sum was $22,085,000.00
    The net change by previously orders $ 1,873,941.00
    The Contract Sum prior to this
    Change Order $23,958,941.00
    The Contract Sum will be
    increased by $ .00
    The new Contract Sum including
    this Change Order will be $23,958,941.00
    The Contract Time will be increased
    by twenty four (24) days
    The new date of Substantial Completion will be August 11, 2022

    Schools named: Jennings Elementary School

    No recorded outcome yet.

    Original agenda text
    2. Grant permission to accept Change Order No. 5 on the Jennings Elementary
    Construction Project.
    
    Change Order #5 reflects the following changes:
    * 24 additional days, due to flooring manufacturing delays
    Bid Changes as follows:
    The Original Contract Sum was $22,085,000.00
    The net change by previously orders $ 1,873,941.00
    The Contract Sum prior to this
    Change Order $23,958,941.00
    The Contract Sum will be
    increased by $ .00
    The new Contract Sum including
    this Change Order will be $23,958,941.00
    The Contract Time will be increased
    by twenty four (24) days
    The new date of Substantial Completion will be August 11, 2022
    MOTION BY: SECONDED BY: PUBLIC COMMENT DISCUSSION VOTE
  3. V.3

    Grant permission to accept Change Order No. 2 on the Jennings High School

    Action Construction & capital $14,994.23

    Canopy Field Lighting and Drainage Project.
    Change Order #2 for $14,994.23 reflects the following changes:
    Item Cor #10 $14,994.23
    ● Catch Basin Interference
    Bid Changes as follows:
    The Original Contract Sum was $1,438,000.00
    The net change by previously orders $ 22,820.06
    The Contract Sum prior to this Change Order $1,460,820.06
    The Contract Sum will be increased by $ 14,994.23
    The new Contract Sum including
    this Change Order will be $1,475,814.29
    The Contract Time will be increased by sixty-eight days (68) days
    The new date of Substantial Completion will be August 11,2022
    To be paid from District 2 Construction

    Schools named: Jennings High School

    No recorded outcome yet.

    Original agenda text
    3. Grant permission to accept Change Order No. 2 on the Jennings High School
    Canopy Field Lighting and Drainage Project.
    Change Order #2 for $14,994.23 reflects the following changes:
    Item Cor #10 $14,994.23
    ● Catch Basin Interference
    Bid Changes as follows:
    The Original Contract Sum was $1,438,000.00
    The net change by previously orders $ 22,820.06
    The Contract Sum prior to this Change Order $1,460,820.06
    The Contract Sum will be increased by $ 14,994.23
    The new Contract Sum including
    this Change Order will be $1,475,814.29
    The Contract Time will be increased by sixty-eight days (68) days
    The new date of Substantial Completion will be August 11,2022
    To be paid from District 2 Construction
    MOTION BY: SECONDED BY: PUBLIC COMMENT DISCUSSION VOTE

VI ADJOURN

  1. VI

    ADJOURN

    Procedural Administrative

    IN COMPLIANCE WITH STATE LAW, A COPY OF THIS AGENDA WAS POSTED IN A CONSPICUOUS PLACE AT THE MEETING PLACE OF
    SAID BOARD ON FRIDAY, JULY 15, 2022 BY 4:00 P.M.
    IN ACCORDANCE WITH THE AMERICAN WITH DISABILITIES ACT, IF YOU NEED SPECIAL ASSISTANCE, PLEASE CONTACT DEBBIE AT
    337-824-1834 DESCRIBING THE ASSISTANCE THAT IS NECESSARY.

    Original agenda text
    VI. ADJOURN
    MOTION BY: SECONDED BY: PUBLIC COMMENT DISCUSSION VOTE
    IN COMPLIANCE WITH STATE LAW, A COPY OF THIS AGENDA WAS POSTED IN A CONSPICUOUS PLACE AT THE MEETING PLACE OF
    SAID BOARD ON FRIDAY, JULY 15, 2022 BY 4:00 P.M.
    IN ACCORDANCE WITH THE AMERICAN WITH DISABILITIES ACT, IF YOU NEED SPECIAL ASSISTANCE, PLEASE CONTACT DEBBIE AT
    337-824-1834 DESCRIBING THE ASSISTANCE THAT IS NECESSARY.

This is not the school board's website

JeffDavisEdu.com is an independent public-information website created, owned and maintained by Brandon Kelley, a candidate for the Jefferson Davis Parish School Board, District 9. It is not operated, funded or endorsed by the Jefferson Davis Parish School Board.

For official school board information, go to www.jeffersondavis.org.

Go to the official website