Should the Jefferson Davis Parish School Board approve: Change Order No. 3 on the JDPSB – Welsh Bond Improvements – Phase 1 Project?
Regular meeting, Nov 19, 2026 · agenda item VI.1.1 · Closed
The agenda item
The board will vote on whether to accept Change Order No. 3 on the JDPSB – Welsh Bond Improvements – Phase 1 project. Contractor: Trahan Construction. It would raise the contract by $67,134.00. It would add 160 days to the contract time. The new completion date would be May 1, 2027.
As written on the agenda
1.1. Change Order No. 3 on the JDPSB – Welsh Bond Improvements – Phase 1 Project.
Consideration to accept Change Order No. 3 on the Welsh Bond Improvements –
Phase 1 — Welsh Upper Elementary School project.
Description: Change Order #3 – Trahan Construction will provide labor and
equipment required for the following:
(refer to attached backup for additional information)
COR #40 – Fence at Front of WES. $50,744, Add 30 Days.
COR #41 — Contract Time Extension. $0.00, Add 100 Days.
COR #43 – 2nd Grade Annex East Door Upgrade. $16,390.00, Add 30 Days.
Details: Change Order #3 for $67,134.00 and adding days: 160 days
Bid Changes as follows:
The Original Contract Sum was $4,699,000.00
The net change by previous orders was $834,462.00
The Contract Sum prior to this Change Order was $5,533,462.00
The Contract Sum will be increased by $67,134.00
The new Contract Sum including this Change Order will be $5,600,596.00
The Contract Time will be increased by one hundred sixty ( 160 ) days
The new date of Substantial Completion will be May 1, 2027
Motion:
Second:
Public Discussion:
Board Discussion:
Vote:
Wording is as published by the school board. Complete official agenda (PDF) · Full meeting record. This poll is unofficial public feedback gathered by JeffDavisEdu.com, not a vote conducted by the school board.
- Choosing Support means you think the board should approve this item as it is written on the agenda.
- Choosing Oppose means you think the board should not approve this item as it is written on the agenda.
Results
3 of 3 said they live in Jefferson Davis Parish. Every response comes from a confirmed email address; one response per email address. This is an advisory poll of people who chose to respond, not a scientific survey.
What the board did
Not yet recorded. The outcome appears here once the minutes of the meeting are published.